The Crinolines that support the boiler cladding have been rolled and await fitting.
The blast pipe base was trial fitted before the smoke box was removed from the frames where it had been sitting.
The cut out in the base of the smoke box had to be enlarged to allow it to sit properly.
Another view of both items.
The super heater header has been subjected to a large amount of machining of the element ports and stud fitting.
The smoke box was then mounted onto the boiler barrel
The view from the opposite side.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.